To determine whether the road construction project is expected to be completed on budget, under budget, or over budget, we can use Cost Variance (CV) and Cost Performance Index (CPI).[ CPI = \frac{EV}{AC} ]

Step 1: Calculate the Cost Performance Index (CPI)

[ CPI = \frac{4,500,000}{9,000,000} = 0.5 ]

A CPI of 0.5 indicates that for every dirham spent, the project is only earning 0.5 dirhams of value.[ AC = 9,000,000 \text{ AED} ]

Step 3: Calculate the Cost Variance (CV)

[ CV = EV - AC = 4,500,000 - 9,000,000 = -4,500,000 \text{ AED} ]

A negative CV means the project is over budget by AED 4,500,000.So, the Earned Value (EV) for the project after 10 weeks is:

[ EV = 30% \times 15,000,000 = 4,500,000 \text{ AED} ]

Step 2: Calculate the Actual Cost (AC)

The actual cost spent after 10 weeks is AED 9,000,000, as provided in the scenario.Cost Performance Index (CPI) CPI is a ratio that indicates the cost efficiency of the project.Cost Variance (CV) Cost Variance is a measure of the difference between the Earned Value (EV) and the Actual Cost (AC).### Conclusion:

  • The Cost Variance (CV) is negative (AED -4,500,000), meaning the project is over budget.### 1.### 2.

النص الأصلي

To determine whether the road construction project is expected to be completed on budget, under budget, or over budget, we can use Cost Variance (CV) and Cost Performance Index (CPI). These two metrics are part of the Earned Value Management (EVM) approach, which helps evaluate a project's financial performance.


1. Cost Variance (CV)


Cost Variance is a measure of the difference between the Earned Value (EV) and the Actual Cost (AC). It helps determine if the project is under or over budget.


[
CV = EV - AC
]


Where:



  • EV (Earned Value): The value of the work actually completed by a specific time.

  • AC (Actual Cost): The actual cost incurred to perform the work by that specific time.


Step 1: Calculate the Earned Value (EV)


We know that the total project cost is AED 15,000,000, and the project was planned to complete 10% of the work each week. After 10 weeks, 30% of the work has been completed. So, the Earned Value (EV) for the project after 10 weeks is:


[
EV = 30% \times 15,000,000 = 4,500,000 \text{ AED}
]


Step 2: Calculate the Actual Cost (AC)


The actual cost spent after 10 weeks is AED 9,000,000, as provided in the scenario.


[
AC = 9,000,000 \text{ AED}
]


Step 3: Calculate the Cost Variance (CV)


[
CV = EV - AC = 4,500,000 - 9,000,000 = -4,500,000 \text{ AED}
]


A negative CV means the project is over budget by AED 4,500,000.


2. Cost Performance Index (CPI)


CPI is a ratio that indicates the cost efficiency of the project. It shows how well the project is performing relative to its budget. A CPI greater than 1 indicates the project is under budget, while a CPI less than 1 indicates the project is over budget.


[
CPI = \frac{EV}{AC}
]


Step 1: Calculate the Cost Performance Index (CPI)


[
CPI = \frac{4,500,000}{9,000,000} = 0.5
]


A CPI of 0.5 indicates that for every dirham spent, the project is only earning 0.5 dirhams of value. This is a sign that the project is significantly over budget.


Conclusion:



  • The Cost Variance (CV) is negative (AED -4,500,000), meaning the project is over budget.

  • The Cost Performance Index (CPI) is 0.5, indicating that the project is not cost-efficient and is likely to end up over budget.


So, the road construction project is expected to be over budget.


تلخيص النصوص العربية والإنجليزية أونلاين

تلخيص النصوص آلياً

تلخيص النصوص العربية والإنجليزية اليا باستخدام الخوارزميات الإحصائية وترتيب وأهمية الجمل في النص

تحميل التلخيص

يمكنك تحميل ناتج التلخيص بأكثر من صيغة متوفرة مثل PDF أو ملفات Word أو حتي نصوص عادية

رابط دائم

يمكنك مشاركة رابط التلخيص بسهولة حيث يحتفظ الموقع بالتلخيص لإمكانية الإطلاع عليه في أي وقت ومن أي جهاز ماعدا الملخصات الخاصة

مميزات أخري

نعمل علي العديد من الإضافات والمميزات لتسهيل عملية التلخيص وتحسينها

آخر التلخيصات

وثّقت مشاهد نشر...

وثّقت مشاهد نشرها المركز الإعلامي للقوات المسلحة اليمنية تنفيذ اللواء السادس طيران مسيّر ضربة جوية ا...

أخـطأ داود الـن...

أخـطأ داود الـنبي عـندمـا أخـذ امـرأة أوریـا الـحثي ووضـعھ فـي مـقدمـة الـجیوش لـیموت وجـاء نـاثـان ...

الاحتراق او الا...

الاحتراق او الانطفاء السياسي شعور المناضل بانطفاء قدرته في النضال الديمقراطي وانطفاء علاقته بزملائه ...

Q E؛ لذا فإن ...

Q E؛ لذا فإن ٥ اقترح أينشتاين أن الإشعاع الكهرومغناطيسي له طبيعة مادية -موجيّة، حيث تعتمد طاقة ال...

ومنذ المرحلة ال...

ومنذ المرحلة الإعدادية، بدأت أحاول أن أتعامل مع كل موضوع أدرسه بطريقة مختلفة. فلم أكن أكتفي بما أتعل...

تتجه قضية نزاع ...

تتجه قضية نزاع على أراضٍ ومجرى سيل في منطقة عقور وادي سلامة بمديرية الصلو، جنوب محافظة تعز اليمنية، ...

[17/03/48 07:58...

[17/03/48 07:58 م] منير فتوح: بر جديده او قديمه جديده حاول انك عن جد تتقصد تتقصد وتتعمد ان تذهب الى ...

تحليل سلوك الشر...

تحليل سلوك الشراء السابق لتقديم توصيات منتجات مخصصة وعروض تناسب ذوق كل عميل.وفي سياق حل بعض المشكلات...

تمكنت الأجهزة ا...

تمكنت الأجهزة الأمنية بمحافظة أبين من ضبط متهم في قضية شروع بالقتل، والسيطرة على حريق نشب في أشجار ا...

أدى اليمين الدس...

أدى اليمين الدستورية أمام فخامة الرئيس الدكتور رشاد محمد العليمي، رئيس مجلس القيادة الرئاسي، اليوم ا...

واصلت القوات ال...

واصلت القوات المسلحة، الجمعة، عملياتها بالطيران المسيّر ضد عناصر وتحركات ومواقع مليشيا الحوثي في تعز...

عُقد اجتماع متخ...

عُقد اجتماع متخصص بعنوان "أزمة الهيمنة الأمريكية وإعادة التشكيل الجيواقتصادي والجيوسياسي في أمريكا ا...

أخبار التقنية