To determine whether the road construction project is expected to be completed on budget, under budget, or over budget, we can use Cost Variance (CV) and Cost Performance Index (CPI).[ CPI = \frac{EV}{AC} ]

Step 1: Calculate the Cost Performance Index (CPI)

[ CPI = \frac{4,500,000}{9,000,000} = 0.5 ]

A CPI of 0.5 indicates that for every dirham spent, the project is only earning 0.5 dirhams of value.[ AC = 9,000,000 \text{ AED} ]

Step 3: Calculate the Cost Variance (CV)

[ CV = EV - AC = 4,500,000 - 9,000,000 = -4,500,000 \text{ AED} ]

A negative CV means the project is over budget by AED 4,500,000.So, the Earned Value (EV) for the project after 10 weeks is:

[ EV = 30% \times 15,000,000 = 4,500,000 \text{ AED} ]

Step 2: Calculate the Actual Cost (AC)

The actual cost spent after 10 weeks is AED 9,000,000, as provided in the scenario.Cost Performance Index (CPI) CPI is a ratio that indicates the cost efficiency of the project.Cost Variance (CV) Cost Variance is a measure of the difference between the Earned Value (EV) and the Actual Cost (AC).### Conclusion:

  • The Cost Variance (CV) is negative (AED -4,500,000), meaning the project is over budget.### 1.### 2.


Original text

To determine whether the road construction project is expected to be completed on budget, under budget, or over budget, we can use Cost Variance (CV) and Cost Performance Index (CPI). These two metrics are part of the Earned Value Management (EVM) approach, which helps evaluate a project's financial performance.


1. Cost Variance (CV)


Cost Variance is a measure of the difference between the Earned Value (EV) and the Actual Cost (AC). It helps determine if the project is under or over budget.


[
CV = EV - AC
]


Where:




  • EV (Earned Value): The value of the work actually completed by a specific time.


  • AC (Actual Cost): The actual cost incurred to perform the work by that specific time.


Step 1: Calculate the Earned Value (EV)


We know that the total project cost is AED 15,000,000, and the project was planned to complete 10% of the work each week. After 10 weeks, 30% of the work has been completed. So, the Earned Value (EV) for the project after 10 weeks is:


[
EV = 30% \times 15,000,000 = 4,500,000 \text{ AED}
]


Step 2: Calculate the Actual Cost (AC)


The actual cost spent after 10 weeks is AED 9,000,000, as provided in the scenario.


[
AC = 9,000,000 \text{ AED}
]


Step 3: Calculate the Cost Variance (CV)


[
CV = EV - AC = 4,500,000 - 9,000,000 = -4,500,000 \text{ AED}
]


A negative CV means the project is over budget by AED 4,500,000.


2. Cost Performance Index (CPI)


CPI is a ratio that indicates the cost efficiency of the project. It shows how well the project is performing relative to its budget. A CPI greater than 1 indicates the project is under budget, while a CPI less than 1 indicates the project is over budget.


[
CPI = \frac{EV}{AC}
]


Step 1: Calculate the Cost Performance Index (CPI)


[
CPI = \frac{4,500,000}{9,000,000} = 0.5
]


A CPI of 0.5 indicates that for every dirham spent, the project is only earning 0.5 dirhams of value. This is a sign that the project is significantly over budget.


Conclusion:



  • The Cost Variance (CV) is negative (AED -4,500,000), meaning the project is over budget.

  • The Cost Performance Index (CPI) is 0.5, indicating that the project is not cost-efficient and is likely to end up over budget.


So, the road construction project is expected to be over budget.


Summarize English and Arabic text online

Summarize text automatically

Summarize English and Arabic text using the statistical algorithm and sorting sentences based on its importance

Download Summary

You can download the summary result with one of any available formats such as PDF,DOCX and TXT

Permanent URL

ٌYou can share the summary link easily, we keep the summary on the website for future reference,except for private summaries.

Other Features

We are working on adding new features to make summarization more easy and accurate


Latest summaries

إن معنى الحياة ...

إن معنى الحياة الأبدية، هذا يظهر جليا في الفصل الذي يتحدث عن قيامة لعازر من آمن بي وإن مات، فسيحيا، ...

استناداً إلى كت...

استناداً إلى كتاب السيد محافظ حمص رقم 4128/ط تاريخ 31/12/2025 وحاشيتكم المسطرة عليه بتكليفي بإجراء ا...

Side panel Sayl...

Side panel Saylor University History of Psychology Back to '1.2: History of Psychology\' Completion...

شهدت الأبحاث ال...

شهدت الأبحاث الطبية والنفسية في السنوات الأخيرة زيادة في الاهتمام بالأمراض المزمنة، بسبب ما تسببه من...

محادثة مع Gemin...

محادثة مع Gemini اريد الاجابة المنطقية والواقعية لديوان المحاسبة الاردني الوحدة 3: كيف يمكن لمدقق في...

الفصل بين السلط...

الفصل بين السلطات والتعاون فيما بينهما . نظام الحكم في دولة الكويت ، يعمل في ظل هيكل دستوري فريد ، ي...

السيادة في الدو...

السيادة في الدولة الفدرالية لا يمكن أن يتوافق مفهوم السيادة في الدولة الدستورية مع الفصل بين السلطات...

كخلاصة لما جاء ...

كخلاصة لما جاء في هذا الفصل، فالسياسة الخارجية الجزائرية بمقارباتها المختلفة حققت العديد من المكاسب ...

لن يعود شيء كما...

لن يعود شيء كما كان بعد نهاية العصر الجليدي، حيث عُزلت جيوب كبيرة من البشرية على جانبي الكرة الأرضية...

كما مٌكن ب عٌ ا...

كما مٌكن ب عٌ الأصل التجاري الإلكترون ،ً فإنه مٌكن تقد مٌه حصة ف شركة والمقصود بتقد مٌ الأصل التجاري...

تغزو سهول شرق أ...

تغزو سهول شرق أفريقيا موطن الغابات التقليدي لأسلافنا من القردة، حيث تقل الأشجار وتتسع المسافات بينها...

الكود الزائف يش...

الكود الزائف يشبه لغات البرمجة مثل C++ ، لكنك لستِ مجبرة على الالتزام بقواعدها الصارمة (Syntax). نحن...