Lakhasly

Online English Summarizer tool, free and accurate!

Summarize result (50%)

Baltimore Aircoil Company equipment needs to be properly installed, operated and maintained.Note: There should be no "chirp" or "squeal" when the fan motor is started. DRIVE ALIGNMENT Proper drive alignment ensures maximum belt life. Alignment is checked for standard drives after correct belt tensioning by placing a straightedge across both sheaves as shown in the Figure below. When the drives are properly aligned the gap measured between straightedge and sheave does not exceed 0,5 mm per 100 mm of fan sheave diameter. 1. Motor Sheave 2. Fan Sheave 3. Points of Contact LOCKING COLLAR The excentric locking collar of the bearing at the drive end ensures that the inner bearing race is secured to the fan shaft. Locking collars can be set using the following procedure. (See Figure below)

  1. Stop fan(s) and remove side access panel(s). 2. Loosen the set screw. 3. Using a drift pin centerpunch, tap the collar (in the hole provided) tangentially in the direction of rotation while holding the shaft. 4. Retighten the screw. 5. Install access panel(s) and start fan(s). 1. Locking Collar
  2. Lubrication Fitting
  3. Extended Lubrication Line ROTATION OF FAN(S) AND PUMP(S) Fans must rotate without obstruction and both fans and pumps must rotate in the correct direction, which is indicated by arrows on the equipment. Check proper functioning as follows:
  4. Stop fan(s) and pump(s). 2. Turn the fan by hand to ensure rotation without obstruction. Remove obstruction, if present. 3. Start the pump(s) and check for the proper rotation as indicated by the arrow on the pump cover. If rotation is wrong, stop pump and correct electrical wiring. 4. Start the fan(s) and check for proper rotation as indicated by the arrow on the fan housing. If rotation is wrong stop fan(s) and correct fan motor wiring. Belt Profile Diameter (mm) Motor Sheave Deflection Force (kg) Min. Max. B 100 through 118 125 through 140 150 through 170

180 1.5 1.5 2.0 2.5 2.0 2.5 2.5 3.0 Table 2: Belt Tension Forces Figure 4: Fan Belt Check and Adjustment Figure 5: Checking sheave alignment Figure 6: Locking Collar Assembly 8 MAINTENANCE PROCEDURES MOTOR VOLTAGE AND CURRENT Check the voltage and the current of all three legs of the motors. The current should not exceed the nameplate rating. After prolonged shutdown the motor insulation should be checked with a megger insulation tester prior to restarting. 1. Insulation resistance test - minimum value should be 1 Mega Ohm (1.000.000 Ohms). 2. Thermistors, if fitted, should be checked for continuity with a multi-meter but never megger-tested. 3. Ensure supply voltage and frequency correspond to the motor nameplate rating. 4. Ensure shaft turns freely. 5. Wire the motor in accordance with the wiring diagram as shown on the motor nameplate and/or in the motor terminal box. 6. Turn on unit and check amp draw does not exceed nameplate rating. Note: If motor is stored, it should be in a clean, dry place & have the shaft rotated occasionally. Storage areas should not be subject to vibration. ! Rapid on-off cycling can cause the fan motor to overheat. It is recommended that controls be set to allow a maximum of 6 on/ off cycles per hour. When two speed motors are used, the motor starter should include a 15 seconds time delay when switching from high to low speed. DRIVE TRAIN

  1. Fan Sheave
  2. Belt
  3. Motor Sheave The DRIVE TRAIN consists of a specially designed belt, a fan sheave and a motor sheave. The high efficiency belt provides the premium quality necessary for evaporative cooling equipment service. Together these components provide a highly reliable system with low maintenance requirements. The DRIVE TRAIN should be inspected periodically to check the belt tension, condition of the sheaves and belt, and when necessary adjust the tension. The recommended service intervals are specified elsewhere. Initial Start-up: If the equipment was supplied in assembled major sections, no servicing is required prior to initial unit start-up since the drive has been tensioned and aligned at the factory. If equipment was supplied completely knocked-down (KD) then check drive alignment & belt tensioning as per procedures outlined above. Seasonal Start-Up: Readjust the tension on the belt. Check condition of sheaves. Operation: After initial unit start-up or the installation of a new belt, the tension must be readjusted after the first 24 hours of operation. Thereafter the condition of the belt should be checked monthly and the tension adjusted as necessary, but at least once every 3 months. ! No service work should be performed on the drive train without first ensuring the fan and pump motors have been isolated, tagged and locked in the off position. UNUSUAL NOISE AND VIBRATIONS Unusual noise and/or vibration are the result of malfunctioning of mechanical components or operational problems (unwanted ice formation). If this occurs, a thoroughful inspection of the entire unit followed by immediate corrective action is needed. If required, consult your local BAC Balticare representative for assistance. GENERAL CONDITION OF THE EQUIPMENT The inspection should focus on following areas:
  • damage of corrosion protection
  • signs of scale formation or corrosion
  • accumulation of dirt an debris
  • presence of biofilms If there is evidence of scale formation (more than 0.1 mm) or corrosion, water treatment regime must be checked and adjusted by the supplier. Any dirt and debris need be removed following the CLEANING PROCEDURE described in this manual (see page 12). If there is evidence of biofilms, the system, including piping, should be drained, flushed and cleaned of slimes and other organic contamination. Refill system with water and apply biocide shock treatment. Check pH value and functionality of ongoing biocide treatment. The RCT Cooling Towers are constructed of corrosion resistant materials. The wet deck surface is made of en inert synthetic material that requires no protection against rot, decay, rust or biological attack. Other materials used in construction of the equipment, that are listed below, should be inspected regularly. Stainless Steel Components Stainless steel components should be inspected for sighs of blemishes or corrosion and cleaned with stainless steel wool as necessary. If more extensive corrosion is prevalent, contact you local BAC-Balticare Representative. Fibreglass Re-Inforced Polyester (FRP) Components FRP components should be inspected for accumulation of dirt and cleaned with soap and water as necessary. Also FRP components should be inspected for any penetration of gelcoat or veil. Such penetrations should be repaired immediately. Figure 7: Drive Train Inspections and Corrective Actions MAINTENANCE PROCEDURES 9 HEAT TRANSFER SECTION The fill should be inspected and cleaned at least quarterly or more regularly if required by local authorities. The inspection procedure is as follows:
  1. Shut off fan(s) and pump(s). 2. Remove the access panel. 3. Inspect the wet deck surface for
  • obstructions
  • damages
  • corrosion
  • fouling. Remove any obstructions from heat transfer section(s). Any damages or corroded areas need to be repaired. Call your local BAC Balticare representative for assistance. Minor fouling can usually be removed chemically or by temporary changes to the water treatment programme. Contact your water treatment supplier for advice. Major fouling requires cleaning and flushing according to the CLEANING PROCEDURES (See page 12). Regular checking of the total aerobic bacteria count (TAB) and maintaining it within acceptable levels are the key to prevent fouling. Note: When working on fill section or above fill section, fill bundle edges should be protected from damage by service personnel, tools or debris by placing a temporary cover of plywood, or other suitable material, over the top of the fill bundles. DRIFT ELIMINATORS The inspection procedure is as follows :
  1. With fan(s) and pump(s) running visually check for areas with excessive drift loss. 2. Shut off fan(s) and pump(s) and visually check eliminators for
  • obstructions
  • damages
  • cleanliness
  • proper fit
  1. If any of the above problems have been observed, stop fan(s) and pump(s) and remove eliminators. 4. Clean eliminators from debris and foreign matter. Remove dirt and obstructions. Replace damaged or ineffective eliminators. 5. Install eliminators and ensure they fit tightly with no gaps. WATER DISTRIBUTION The inspection procedure is as follows :
  2. Shut off the fan(s), but leave the pump(s) running. 2. Check and adjust spray pressure, if required. 3. Remove the eliminators. 4. Check to see if the nozzles are producing the spray pattern shown in figure(s) below
  3. Clean water distribution from dirt and debris. Ensure spray branches and nozzles are in place and clean. Replace damaged or missing nozzles. 6. Install eliminators and ensure they fit tightly with no gaps. 7. Start fan(s) and pump(s). COMBINED INLET SHIELDS Combined inlet shields are installed at the air inlet side. These will prevent UV light from shining into the sump water and will eliminate the suction of large airborne impurities and debris. In addition, they will prevent water from splashing out of the air intake side of the unit during fan cycling. Figure 8: Removable Fill Figure 9: Removable Drift Eliminators Figure 10: Nozzle Spray Distribution Type Cooling Tower Figure 11: Removable Spray System 10 MAINTENANCE PROCEDURES Inspect regularly and remove foreign objects that might impair air passage. Replace broken and missing parts when necessary. Failure to replace broken shields will result in water loss due to splash out. You can remove the Combined Inlet Shields by simple loosening a single bolt on both ends of the air intake side. This allows simple removal of the combined inlet shields in small and easy to handle sections allowing full access to the sump section for maintenance. . Figure 12: Remove Combined Inlet Shields FAN SHAFT The fan shaft is fabricated from stainless steel. The exposed areas of the fan shaft are coated with a soft seal for added corrosion protection. It is recommended that the coating be inspected for continuity quarterly or at least every 6 months. Any signs of surface corrosion must be treated. This involves:
  4. Removal of the protective coating with a suitable cleaning medium
  5. The removal of any surface corrosion with emery cloth
  6. The re-coating of the shaft with soft seal. AXIAL FAN Due to its size and speed, the axial fan has great potential for injury and destruction if damaged. Inspect closely, and as required, replace damaged or deteriorating fan blades. Inspection should include the fan, fan cylinder and fan guard, and these should be inspected for
  • Fan blade tip clearance
  • Pitch angle
  • Bolt torque
  • Excessive vibration
  • Deterioration of fan assembly Correct or adjust if necessary. Note: Before any disassembly, fan blades and hub should be match marked to ensure proper blade pitch angle when reassembled. ! No service work should be performed on or near the fans, motors, and drives or inside the unit without first ensuring the fan and pump motors have been isolated, tagged and locked in the off position. FAN MOTOR The standard fan motor for this line of units is a TEFC (Totally Enclosed Fan Cooled) motor. The motor with frame size smaller or equal than 200L has permanently lubricated ball bearings and special moisture protection on the bearings, shaft and windings. The only servicing required during operation is to clean the outside surface of the motor at least quarterly to ensure proper motor cooling. After prolonged shutdowns, the motor insulation should be checked with a "megger" insulation tester before restarting the motor.(Contact your local BAC Balticare representative for advice.) Whenever two speed motors are used for capacity control, a time delay of at least 15 seconds is required when switching form high to low speed. Sudden switch over might damage the drive system or the motor. Note: When operating with VFD drives above nominal frequency be aware of the potential risk for motor overload or mechanical damages. Note: It is recommended to provide sinus filters on the VFD to prevent bearing damage on fan motors. ! Please refer to fan motor nameplate data when programming a VFD. The purpose of a Low Level Cut out Switch is to protect the pump from running dry in case of make-up failure or extreme water loss. The status of the alarm can be checked prior to pump start-up, but should not be considered during the first minute after start-up, since activation of the pump can cause a water level drop, that might trigger the alarm. Normal make-up will stabilize the water level after a short period of time. About Cold Weather Operation Protection Against Sump Water Freezing Capacity Control 6 MAINTENANCE PROCEDURES COLD WATER BASIN AND BASIN STRAINERS The cold water basin should be inspected regularly. Any debris which may have accumulated in the basin or on the strainers should be removed. Quarterly, or more often if necessary, the entire cold water basin should be drained, cleaned and flushed with fresh water to remove the silt and sediment which normally collects in the basin and under the wet deck surface during operation. When flushing the basin, the strainers should be left in place to prevent the sediment from re-entering the unit system. After the basin has been flushed, the strainers should be removed, cleaned, and replaced before refilling the basin with fresh water. ! DO NOT USE ACID TO CLEAN THE STRAINERS Remote Basin The water level in the basin of equipment designed for remote basin operation is a function of the circulating water flow rate; water outlet connection size, quantity and location, and outlet piping size and configuration. The remote basin unit is supplied without a water make-up assembly or a strainer and the basin operating level during remote basin operation is not adjustable. OPERATING LEVEL AND MAKE-UP As the water circulating through the tower is cooled, it collects in the cold water basin and passes through the strainers into the system. The operating water level is controlled by the make-up valve and should be maintained at an operating water level of 140 mm below ledge on which louvres rest. Because the typical winter load is less than the summer load, the winter evaporation rate is frequently less than the summer evaporation rate. With this reduced evaporation rate in winter, the water level in the cold water basin will increase unless the float is readjusted. The operating water level should be checked monthly and float readjusted as necessary to maintain the recommended operating level. A float operated water make-up assembly is furnished as standard equipment on cooling towers. It is located inside the unit within easy reach from the access door. The float is mounted on an all-thread rod which is held in place by wing nuts. The operating water level in the cold water basin can be adjusted by repositioning the float and all-thread rod using the wing nuts provided. The make-up assembly should be inspected monthly and adjusted as necessary. The valve itself should be inspected annually for leakage and the valve seat replaced if necessary. The make-up water supply pressure should be maintained between 100 and 450 kPa for proper operation of the valve. To make the initial basin water level setting, fill the sump with water until 2 cm above the operating level. Adjust the wing nuts of the float ball so that the make-up valve is completely closed. Under normal load conditions this setting should produce the correct operating level. At low load conditions the operating level will rise and needs to be adjusted. The unit basin should be closely monitored and water level adjusted as necessary during the first 24 hours of operation. 1. Float Ball
  1. All Threaded rod
  2. Wing Nuts
  3. Float Arm Assembly
  4. Float Valve BLOW DOWN In case of a continuous blow down with a metering valve in the bleed line, ensure that the valve is unobstructed and that blow down water can drain freely. Measure the blow down flow rate by recording the time needed to fill a given volume. For automatic blow down using conductivity control, ensure that the conductivity probe is clean and that the blow down solenoid valve is operational. Unless you have a specific adjustment procedure, your water treatment company should check and adjust set points. Under no circumstances should sump heaters operate at other times as they could potentially heat the water to temperature levels, which are favourable to bacteriological growth. Ensure every six months the heater thermostat is properly set and clean. Also ensure that control and safety devices, such as low level cut out switches, are operational, clean and properly incorporated into the control circuit. ! SUMP HEATERS CAN BE HOT. BELT TENSIONING Belt tensioning can be checked as follows:
    1. Rotate the fan sheave half a turn to evenly distribute the tension in the belt before measuring. 3. Check belt tension by verifying both following conditions: the deflection amounts 10 mm/m free belt length (see figure below) the deflection force required is between the minimum and maximum values given in the table below.Figure 15: Ball Bearing Shell Alvania grease RL3 -20?C to +120?C Texaco Multifak Premium 3 -30?C to +140?C Kluber Isoflex LDS Special A -50?C to +120?C Mobil Mobilith SHC 100 -40?C to +175?C Total Fina Elf Multis 3 -20?C to +120?C Table 3: Grease Products Figure 16: Ball Bearing Figure 17: Adjustable Motor Base 12 MAINTENANCE PROCEDURES MECHANICAL CLEANING Keeping your evaporative cooling equipment (and the associated system) clean will maintain its efficiency and help to prevent uncontrolled bacteriological growth.For the cooling system, scale, corrosion and biological control must be established and initiated when the system is first filled with water and administered on a regular basis thereafter in accordance with recognized Codes of Practice, (such as EUROVENT 9 - 5/6, ACOP HSC L8, Guide des bonnes pratiques, Legionella et tours aerorefrigerantes, etc.).To facilitate servicing of the equipment, it is suggested that the following parts be carried on hand :
  • Make-up float ball (if applicable)
  • Valve seal for water make-up valve
  • Fan shaft bearings
  • Spray nozzles and grommets
  • Spray distribution branch grommets
  • Set of belts Insist on factory authorised parts to avoid loss of efficiency or an operational risk, which may occur if non-authorised parts are used.On a quarterly or six monthly basis check:
  • electric connections
  • motor protection devices
  • check amp draw
  • motor bearings for noise/overheating
  • motor holding bolts
  • external surface of motor for corrosion If the motor is equipped with space heaters, these must be activated when the motor is idle in order to prevent condensation inside the motor.Cleaning Procedures COMPREHENSIVE MAINTENANCE 13 In order to ensure maximum efficiency and minimum downtime of your evaporative cooling system, it is recommended to establish and execute a programme of preventive maintenance.Temperature increase due to sun radiation could deform the fill or eliminators AUTHORIZED PERSONNEL The operation, maintenance and repair of this equipment should be undertaken only by personnel authorized and qualified to do so. All such personnel should be thoroughly familiar with the equipment, the associated systems and controls and the procedures set forth in this and other relevant manuals.Depending upon site conditions it also may be necessary to install items such as bottom screens, ladders, safety cages, stairways, access platforms, handrails and toe boards for the safety and convenience of the authorized service and maintenance personnel.Accordingly a treatment programme specifically designed to address biological control should be initiated when the system is first filled with water and administered on a regular base thereafter in accordance with any regulations (national, regional) that may exist or in accordance with accepted codes of good practice, such as EUROVENT 9-5/6, VDMA Detailsheet 24649 etc.Consult your water treatment specialist for specific recommendation About Water Care Pultruded Composite pH 6.5 to 9.5 pH during initial passivation Not Applicable Total hardness as (CaCO3) 750 mg/l Total alkalinity as (CaCO3) 600 mg/l max.The preventive maintenance programme must not only avoid that excessive downtime occurs under unforeseen and unwanted conditions, but must also ensure that factory authorized replacement parts are used, which are designed to fit and for their purpose carry the full factory warranty.Passivation is the formation of a protective, passive, oxide layer on galvanized steel surfaces.Motor Sheave 4.!2.2.1.2.3.!!1.1.2.3.4.5.6.7.8.9.


Original text

Baltimore Aircoil Company equipment needs to be
properly installed, operated and maintained.
Documentation of the equipment used, including a
drawing, technical data sheet and this manual should be
kept on record. To achieve long, trouble-free and safe
operation, it is necessary to establish an operating plan
including a programme of regular inspection, monitoring
and maintenance. All inspections, maintenance and
monitoring actions should be recorded in a cooling system
logbook. The operating and maintenance instructions
published here can be used as a guide to achieve these
goals.
In addition to establishing the operating plan and the
cooling system logbook it is recommended to conduct a
cooling system risk analysis, preferably by an independent
third party.
For the cooling system, scale, corrosion and biological
control must be established and initiated when the system
is first filled with water and administered on a regular
basis thereafter in accordance with recognized Codes of
Practice, (such as EUROVENT 9 - 5/6, ACOP HSC L8, Guide
des bonnes pratiques, Legionella et tours
aéroréfrigérantes, etc.). Water sampling, test results and
corrective actions should be recorded in the cooling
system logbook.
For more specific recommendations on keeping your
cooling system efficient and safe, contact your local BAC
Balticare service provider or representative. Name, e-mail
and phone number can be found on the website
www.BACservice.eu.
Table of Contents page
Construction Details 2
General Information 3
Water Care 4
Cold Weather Operations 5
Maintenance Procedures 6
Comprehensive Maintenance 13
Further Assistance & Information 14
2
CONSTRUCTION DETAILS
TYPICAL CROSS SECTION



  1. Water Distribution System

  2. Eliminators (not shown)

  3. Fill

  4. Cold Water Basin

  5. Strainer

  6. Drain

  7. Overflow

  8. Make-up Assembly & Quick Fill

  9. Louvres

  10. Fan Shaft (not shown)

  11. Fan (not shown)

  12. Drive Train (not shown)

  13. Motor Base (not shown)

  14. Motor

  15. Access door (not shown)
    Note: Models RCT-2118 and RCT-2129 are direct drive and do not have drive
    train.
    RCT Cooling Towers
    GENERAL INFORMATION
    3
    BAC cooling equipment is designed for the operating conditions
    specified below, which must not be exceeded during operation.
    Wind Load: For safe operation of unshielded equipment exposed to
    wind speeds above 120 km/h installed at a height above 30 m from
    the ground contact your local BAC-Balticare representative.
    Seismic Risk: For safe operation of equipment installed in moderate
    and high hazard area’s contact your local BAC Balticare
    representative.
    Standard electrical motors are suitable for an ambiant temperature
    range from -25°C to +40°C.
    COOLING TOWERS
    Maximum inlet pressure : 0.5 bar
    Water inlet temperature : max. 55°C (std. fill) or 65°C (high
    temperature option)
    Water outlet temperature : min. 5°C
    For circulating water quality compatible with construction materials
    refer to section ‘WATER CARE’ on page 4.
    Note: Actual spray pressure is indicated on technical data sheet supplied with
    order acknowledgement.
    All piping external to BAC cooling equipment must be supported
    separately. In case the equipment is installed on vibration rails or
    springs, the piping must contain compensators to eliminate
    vibrations carried through the external pipework.
    All electrical, mechanical and rotating machinery constitute a
    potential hazard, particularly for those not familiar with its design,
    construction and operation. Accordingly, adequate safeguards
    (including use of protective enclosures where necessary) should be
    taken with this equipment both to safeguard the public (including
    minors) from injury and to prevent damage to the equipment, its
    associated system and the premises.
    If there is doubt about safe and proper rigging, installation,
    operation or maintenance procedures, contact the equipment
    manufacturer or his representative for advise.
    When working on operating equipment, be aware that some parts
    may have an elevated temperature. Any operations on elevated
    level have to be executed with extra care to prevent accidents.
    !
    Do not cover units with PVC eliminators or fill with a plastic
    tarpaulin. Temperature increase due to sun radiation could
    deform the fill or eliminators
    AUTHORIZED PERSONNEL
    The operation, maintenance and repair of this equipment should be
    undertaken only by personnel authorized and qualified to do so. All
    such personnel should be thoroughly familiar with the equipment,
    the associated systems and controls and the procedures set forth in
    this and other relevant manuals. Proper care, procedures and tools
    must be used in handling, lifting, installing, operating and repairing
    this equipment to prevent personal injury and/or property damage.
    MECHANICAL SAFETY
    Mechanical safety of the equipment is in accordance with the
    requirements of the EU machinery directive. Depending upon site
    conditions it also may be necessary to install items such as bottom
    screens, ladders, safety cages, stairways, access platforms,
    handrails and toe boards for the safety and convenience of the
    authorized service and maintenance personnel. At no time this
    equipment should be operated without all fan screens, access
    panels and access doors in place.
    When the equipment is operated with a variable fan speed control
    device, steps must be taken to avoid operating at or near to the
    fan’s «critical speed». For more information consult your local BAC
    Balticare representative.
    ELECTRICAL SAFETY
    Each fan and pump motor associated with this equipment should be
    installed with a lockable disconnect switch located within the sight
    of the equipment. No service work should be performed on or near
    the fans, motors, drives or inside the equipment unless fan and
    pump motors, heaters etc. are electrically isolated.
    LOCATION
    All cooling equipment should be located as far away as possible
    from occupied areas, open windows or air intakes to buildings.
    LOCAL REGULATIONS
    Installation and operation of cooling equipment may be subject of
    local regulations, such as establishment of risk analysis. Ensure
    regulatory requirements are consistently met.
    Operating Conditions
    Connecting Pipework
    Safety Precautions
    4
    WATER CARE
    In all cooling equipment, operating in evaporative mode, the cooling
    is accomplished by evaporating a small portion of the re-circulating
    water as it flows through the equipment. When this water
    evaporates, the impurities originally present in the water remain.
    Unless a small amount of water is drained from the system, known
    as blow down, the concentration of dissolved solids will increase
    rapidly and lead to scale formation or corrosion or both. Also, since
    water is being lost from the system through evaporation and blow
    down, this water needs to be replenished.
    The total amount of replenishment, known as make-up, is defined
    as:
    Make-up = evaporation loss + blow down
    In addition to the impurities present in the make-up water, any
    airborne impurities or biological matter are carried into the
    equipment and drawn into the re-circulating water. Over and above
    the necessity to blow down a small quantity of water, a water
    treatment programme specifically designed to address scale,
    corrosion and biological control should be initiated when the system
    is first installed and maintained on a continuous base thereafter.
    Moreover there must be an ongoing programme of monitoring in
    place to ensure the water treatment system is maintaining the
    water quality within the control guidelines.
    Check and adjustments of blow down depends on the blow down
    device actual in use.
    To prevent excessive build-up of impurities in the circulating water, a
    small amount of water must be « bled » from the system at a rate to
    be determined by the water treatment regime. The amount of blow
    down is determined by the design cycles of concentration for the
    system. These cycles of concentration depend on the quality of the
    make-up water and the design guidelines for the quality of the
    recirculating water given below.
    Make-up water to the evaporative unit should have minimum 30
    ppm hardness as CaCO3.
    Where use of a softener is necessary to achieve this, the supply to
    the evaporative unit should not be totally softened, but blended with
    the incoming unsoftened water to achieve the minimum hardness
    between 30 and 70 ppm as Ca CO3.
    Maintaining a minimum hardness in the make-up water offsets the
    corrosive properties of totally softened water and reduces the
    reliance on corrosion inhibitors to protect the system.
    Note: (*)Higher concentration of sulphates is allowed, provided the sum of
    chlorides + sulphates paramteters does not exceed 1500 mg/l for Pultruded
    composite.
    Cycles of concentration are the ratio of the dissolved solids
    concentration in the circulating water compared to the dissolved
    solids concentration in the make-up water. The blow down rate can
    be calculated as follows :
    Blow down = Evaporation loss / Cycles of concentration - 1
    The evaporation loss is not only function of the heat load but also
    depends on climatic conditions, the type of equipment used and the
    method of capacity control, which is applied. The evaporation loss at
    summer conditions is approximately 0.431 l/ 1000 kJ heat
    rejection. This number should be used for blow down valve sizing
    only and not for the calculation of annual water consumption.
    The growth of algae, slimes and other micro-organisms, if
    uncontrolled, will reduce system efficiency and may contribute to
    the growth of potentially harmful micro-organisms, such as
    Legionella, in the recirculating water system.
    Accordingly a treatment programme specifically designed to
    address biological control should be initiated when the system is
    first filled with water and administered on a regular base thereafter
    in accordance with any regulations (national, regional) that may
    exist or in accordance with accepted codes of good practice, such as
    EUROVENT 9-5/6, VDMA Detailsheet 24649 etc.
    It is strongly recommended to monitor the bacteriological
    contamination of the recirculating water on a regular base (for
    example, TAB test with dip slides on a weekly base) and record all
    results. Water treatment should meet the following requirements:

  16. The chemicals must be compatible with the materials of
    construction used in the cooling system.

  17. Chemicals should be fed into the re-circulated water to avoid
    localised high concentrations, which may cause corrosion.
    Chemicals are normally fed into the pump discharge line. Batch
    feeding of chemicals does not afford adequate control of water
    quality and is not recommended.
    It is strongly recommended to check the key parameters of the
    circulating water quality on a monthly base. See Table: Circulated
    Water Quality Guidelines. All test results need be recorded.
    When new systems are first commissioned, special measures
    should be taken to ensure that galvanized steel surfaces are
    properly passivated to provide maximum protection from corrosion.
    Passivation is the formation of a protective, passive, oxide layer on
    galvanized steel surfaces. To ensure that galvanized steel surfaces
    are passivated, the pH of circulating water should be kept between
    7.0 and 8.2 and calcium hardness between 100 and 300 ppm (as
    CaCO3) for four to eight weeks after start-up, or until new zinc
    surfaces turn dull grey in colour. If white deposits form on
    galvanized steel surfaces after the pH is returned to normal service
    levels, it may be necessary to repeat the passivation process.
    Note: Stainless steel units and units protected by the BALTIBOND® hybrid
    coating, without galvanized coil, do not require passivation.
    In case you can’t keep the pH below 8.2, a secondary approach is to
    conduct a chemical passivation using inorganic phosphate or filmforming passivation agents. Consult your water treatment specialist
    for specific recommendation
    About Water Care
    Pultruded Composite
    pH 6.5 to 9.5
    pH during initial passivation Not Applicable
    Total hardness as (CaCO3) 750 mg/l
    Total alkalinity as (CaCO3) 600 mg/l max.
    Total Dissolved Solids 2500 mg/l max.
    Conductivity 4000 µS/cm
    Chlorides 750 mg/l max.
    Sulfates() 750 mg/l max.()
    Total suspended solids 25 mg/l max.
    Chlorination (as free chlorine): continuous
    2 mg / l max.
    Chlorination (as free chlorine): batch
    dosing for cleaning & disinfection
    5-15 mg/l max. for 6 hours max.
    25 mg/l max. for 2 hours max.
    50 mg/l max. for 1 hour max.
    Table 1: Circulated Water Quality Guidelines for Pultruded Composite
    Biological Control
    Chemical Treatment
    Passivation
    COLD WEATHER OPERATIONS
    5
    BAC equipment can be operated in subfreezing ambient conditions
    provided the proper measures are taken :

  18. Protection against sump water freezing, when the system is idle.

  19. Capacity control to prevent ice formation during operation.
    Listed below are general guidelines, which should be followed to
    minimise the possibility of freeze-up. As these guidelines may not
    include all aspects of the anticipated operation scheme, system
    designer and operator must thoroughly review the system, location
    of the equipment, controls and accessories to ensure reliable
    operation at all times.
    To prevent sump water from freezing, either sump heaters or a
    remote sump located in a heated indoor area must be installed. For
    a seasonal shut down during the cold weather period, it is
    recommended to drain the sump.
    Thermostats for electrical sump heaters for this equipment are set
    to maintain a sump water temperature of 4°C.
    In addition to protecting the sump water, all exposed water piping, in
    particular make-up water lines should be heat traced and insulated.
    It is necessary to prevent the recirculating water from approaching
    freezing conditions when the system is operating under load. The
    most « critical » situation occurs, if operation at subfreezing
    conditions coincides with light load conditions. The key to protecting
    the recirculating water is capacity control by adjustment of airflow
    to maintain the temperature of the recirculating water minimal
    above freezing point. As a rule of thumb this minimum temperature
    is 5°C, but there are applications, where even lower temperatures
    can be accepted. (Contact your local BAC Balticare representative
    for advice.)
    Whenever two speed motors are used for capacity control, a time
    delay of at least 15 seconds is required when switching form high to
    low speed. Sudden switch over might damage the drive system or
    the motor.
    Note: When operating with VFD drives above nominal frequency be aware of
    the potential risk for motor overload or mechanical damages.
    Note: It is recommended to provide sinus filters on the VFD to prevent bearing
    damage on fan motors.
    !
    Please refer to fan motor nameplate data when
    programming a VFD.
    The purpose of a Low Level Cut out Switch is to protect the pump
    from running dry in case of make-up failure or extreme water loss.
    The status of the alarm can be checked prior to pump start-up, but
    should not be considered during the first minute after start-up, since
    activation of the pump can cause a water level drop, that might
    trigger the alarm. Normal make-up will stabilize the water level after
    a short period of time.
    About Cold Weather Operation
    Protection Against Sump Water Freezing
    Capacity Control
    6
    MAINTENANCE PROCEDURES
    COLD WATER BASIN AND BASIN STRAINERS
    The cold water basin should be inspected regularly. Any debris
    which may have accumulated in the basin or on the strainers should
    be removed. Quarterly, or more often if necessary, the entire cold
    water basin should be drained, cleaned and flushed with fresh water
    to remove the silt and sediment which normally collects in the basin
    and under the wet deck surface during operation.
    When flushing the basin, the strainers should be left in place to
    prevent the sediment from re-entering the unit system. After the
    basin has been flushed, the strainers should be removed, cleaned,
    and replaced before refilling the basin with fresh water.
    !
    DO NOT USE ACID TO CLEAN THE STRAINERS
    Remote Basin
    The water level in the basin of equipment designed for remote basin
    operation is a function of the circulating water flow rate; water
    outlet connection size, quantity and location, and outlet piping size
    and configuration. The remote basin unit is supplied without a water
    make-up assembly or a strainer and the basin operating level during
    remote basin operation is not adjustable.
    OPERATING LEVEL AND MAKE-UP
    As the water circulating through the tower is cooled, it collects in the
    cold water basin and passes through the strainers into the system.
    The operating water level is controlled by the make-up valve and
    should be maintained at an operating water level of 140 mm below
    ledge on which louvres rest.
    The operating water level in the cold water basin will vary somewhat
    with system thermal load (evaporation rate), the bleed rate
    employed and the make-up water supply pressure. Because the
    typical winter load is less than the summer load, the winter
    evaporation rate is frequently less than the summer evaporation
    rate. With this reduced evaporation rate in winter, the water level in
    the cold water basin will increase unless the float is readjusted. The
    operating water level should be checked monthly and float readjusted as necessary to maintain the recommended operating
    level.
    A float operated water make-up assembly is furnished as standard
    equipment on cooling towers. It is located inside the unit within easy
    reach from the access door.
    The standard make-up assembly (see figure below) consists of a
    make-up valve connected to a float arm assembly and actuated by a
    large diameter plastic float. The float is mounted on an all-thread
    rod which is held in place by wing nuts. The operating water level in
    the cold water basin can be adjusted by repositioning the float and
    all-thread rod using the wing nuts provided.
    The make-up assembly should be inspected monthly and adjusted
    as necessary. The valve itself should be inspected annually for
    leakage and the valve seat replaced if necessary. The make-up
    water supply pressure should be maintained between 100 and 450
    kPa for proper operation of the valve.
    To make the initial basin water level setting, fill the sump with water
    until 2 cm above the operating level. Adjust the wing nuts of the
    float ball so that the make-up valve is completely closed. Before
    starting the unit for the first time, fill the sump until 1 cm below
    overflow level (push float ball under). Under normal load conditions
    this setting should produce the correct operating level. At low load
    conditions the operating level will rise and needs to be adjusted. The
    unit basin should be closely monitored and water level adjusted as
    necessary during the first 24 hours of operation.

  20. Float Ball

  21. All Threaded rod

  22. Wing Nuts

  23. Float Arm Assembly

  24. Float Valve
    BLOW DOWN
    In case of a continuous blow down with a metering valve in the
    bleed line, ensure that the valve is unobstructed and that blow down
    water can drain freely. Measure the blow down flow rate by
    recording the time needed to fill a given volume.
    For automatic blow down using conductivity control, ensure that the
    conductivity probe is clean and that the blow down solenoid valve is
    operational. Unless you have a specific adjustment procedure, your
    water treatment company should check and adjust set points.
    Checks and Adjustments
    Figure 1: Basin Strainer
    Figure 2: Mechanical Float Assembly
    Figure 3: Water Make-up Valve Assembly
    MAINTENANCE PROCEDURES
    7
    SUMP HEATER PACKAGE
    Sump heaters must only operate in the winter to prevent the sump
    water from freezing, when the water pump(s) and the fan(s) are shut
    off. Under no circumstances should sump heaters operate at other
    times as they could potentially heat the water to temperature levels,
    which are favourable to bacteriological growth. Ensure every six
    months the heater thermostat is properly set and clean. Also ensure
    that control and safety devices, such as low level cut out switches,
    are operational, clean and properly incorporated into the control
    circuit.
    !
    SUMP HEATERS CAN BE HOT.
    BELT TENSIONING
    Belt tensioning can be checked as follows:

  25. Shut off fan(s).

  26. Rotate the fan sheave half a turn to evenly distribute the tension
    in the belt before measuring.

  27. Check belt tension by verifying both following conditions:
    the deflection amounts 10 mm/m free belt length (see figure
    below)
    the deflection force required is between the minimum and
    maximum values given in the table below.

  28. Fan Sheave

  29. Belt

  30. Motor Sheave

  31. 10 mm/m Deflection = Proper Belt Tension

  32. Straight Edge
    New belts have to be re-tensioned after 24 hours operation.
    If Belt tensioning is required, please proceed as follows:

  33. Loosen the lock nuts on the Motor Base Adjusting Screws.

  34. Turn the Motor Base Adjusting Screws clockwise to tension the
    belt, or counter-clockwise to relieve belt tension. During
    adjustment of belt tension the drives should be rotated several
    times by hand to evenly distribute the tension throughout the
    belt.

  35. When the belt is properly tensioned, retighten the locking nuts
    on the Motor Base Adjusting Screws.
    Note: There should be no “chirp” or “squeal” when the fan motor is started.
    DRIVE ALIGNMENT
    Proper drive alignment ensures maximum belt life. Alignment is
    checked for standard drives after correct belt tensioning by placing
    a straightedge across both sheaves as shown in the Figure below.
    When the drives are properly aligned the gap measured between
    straightedge and sheave does not exceed 0,5 mm per 100 mm of
    fan sheave diameter.

  36. Motor Sheave

  37. Fan Sheave

  38. Points of Contact
    LOCKING COLLAR
    The excentric locking collar of the bearing at the drive end ensures
    that the inner bearing race is secured to the fan shaft. Locking
    collars can be set using the following procedure. (See Figure below)

  39. Stop fan(s) and remove side access panel(s).

  40. Loosen the set screw.

  41. Using a drift pin centerpunch, tap the collar (in the hole provided)
    tangentially in the direction of rotation while holding the shaft.

  42. Retighten the screw.

  43. Install access panel(s) and start fan(s).

  44. Locking Collar

  45. Lubrication Fitting

  46. Extended Lubrication Line
    ROTATION OF FAN(S) AND PUMP(S)
    Fans must rotate without obstruction and both fans and pumps
    must rotate in the correct direction, which is indicated by arrows on
    the equipment. Check proper functioning as follows:

  47. Stop fan(s) and pump(s).

  48. Turn the fan by hand to ensure rotation without obstruction.
    Remove obstruction, if present.

  49. Start the pump(s) and check for the proper rotation as indicated
    by the arrow on the pump cover. If rotation is wrong, stop pump
    and correct electrical wiring.

  50. Start the fan(s) and check for proper rotation as indicated by the
    arrow on the fan housing. If rotation is wrong stop fan(s) and
    correct fan motor wiring.
    Belt Profile Diameter (mm)
    Motor Sheave
    Deflection Force (kg)
    Min. Max.
    B 100 through 118
    125 through 140
    150 through 170



180
1.5
1.5
2.0
2.5
2.0
2.5
2.5
3.0
Table 2: Belt Tension Forces
Figure 4: Fan Belt Check and Adjustment
Figure 5: Checking sheave alignment
Figure 6: Locking Collar Assembly
8
MAINTENANCE PROCEDURES
MOTOR VOLTAGE AND CURRENT
Check the voltage and the current of all three legs of the motors.
The current should not exceed the nameplate rating. After
prolonged shutdown the motor insulation should be checked with a
megger insulation tester prior to restarting.




  1. Insulation resistance test – minimum value should be 1 Mega
    Ohm (1.000.000 Ohms).

  2. Thermistors, if fitted, should be checked for continuity with a
    multi-meter but never megger-tested.

  3. Ensure supply voltage and frequency correspond to the motor
    nameplate rating.

  4. Ensure shaft turns freely.

  5. Wire the motor in accordance with the wiring diagram as shown
    on the motor nameplate and/or in the motor terminal box.

  6. Turn on unit and check amp draw does not exceed nameplate
    rating.
    Note: If motor is stored, it should be in a clean, dry place & have the shaft
    rotated occasionally. Storage areas should not be subject to vibration.
    !
    Rapid on-off cycling can cause the fan motor to overheat.
    It is recommended that controls be set to allow a maximum of 6 on/
    off cycles per hour. When two speed motors are used, the motor
    starter should include a 15 seconds time delay when switching from
    high to low speed.
    DRIVE TRAIN

  7. Fan Sheave

  8. Belt

  9. Motor Sheave
    The DRIVE TRAIN consists of a specially designed belt, a fan sheave
    and a motor sheave. The high efficiency belt provides the premium
    quality necessary for evaporative cooling equipment service.
    Together these components provide a highly reliable system with
    low maintenance requirements. The DRIVE TRAIN should be
    inspected periodically to check the belt tension, condition of the
    sheaves and belt, and when necessary adjust the tension. The
    recommended service intervals are specified elsewhere.
    Initial Start-up: If the equipment was supplied in assembled major
    sections, no servicing is required prior to initial unit start-up since
    the drive has been tensioned and aligned at the factory. If
    equipment was supplied completely knocked-down (KD) then check
    drive alignment & belt tensioning as per procedures outlined above.
    Seasonal Start-Up: Readjust the tension on the belt. Check
    condition of sheaves.
    Operation: After initial unit start-up or the installation of a new belt,
    the tension must be readjusted after the first 24 hours of operation.
    Thereafter the condition of the belt should be checked monthly and
    the tension adjusted as necessary, but at least once every 3
    months.
    !
    No service work should be performed on the drive train without
    first ensuring the fan and pump motors have been isolated,
    tagged and locked in the off position.
    UNUSUAL NOISE AND VIBRATIONS
    Unusual noise and/or vibration are the result of malfunctioning of
    mechanical components or operational problems (unwanted ice
    formation). If this occurs, a thoroughful inspection of the entire unit
    followed by immediate corrective action is needed. If required,
    consult your local BAC Balticare representative for assistance.
    GENERAL CONDITION OF THE EQUIPMENT
    The inspection should focus on following areas:



  • damage of corrosion protection

  • signs of scale formation or corrosion

  • accumulation of dirt an debris

  • presence of biofilms
    If there is evidence of scale formation (more than 0.1 mm) or
    corrosion, water treatment regime must be checked and adjusted
    by the supplier.
    Any dirt and debris need be removed following the CLEANING
    PROCEDURE described in this manual (see page 12).
    If there is evidence of biofilms, the system, including piping, should
    be drained, flushed and cleaned of slimes and other organic
    contamination. Refill system with water and apply biocide shock
    treatment. Check pH value and functionality of ongoing biocide
    treatment.
    The RCT Cooling Towers are constructed of corrosion resistant
    materials. The wet deck surface is made of en inert synthetic
    material that requires no protection against rot, decay, rust or
    biological attack. Other materials used in construction of the
    equipment, that are listed below, should be inspected regularly.
    Stainless Steel Components
    Stainless steel components should be inspected for sighs of
    blemishes or corrosion and cleaned with stainless steel wool as
    necessary. If more extensive corrosion is prevalent, contact you local
    BAC-Balticare Representative.
    Fibreglass Re-Inforced Polyester (FRP) Components
    FRP components should be inspected for accumulation of dirt and
    cleaned with soap and water as necessary. Also FRP components
    should be inspected for any penetration of gelcoat or veil. Such
    penetrations should be repaired immediately.
    Figure 7: Drive Train
    Inspections and Corrective Actions
    MAINTENANCE PROCEDURES
    9
    HEAT TRANSFER SECTION
    The fill should be inspected and cleaned at least quarterly or more
    regularly if required by local authorities.
    The inspection procedure is as follows:



  1. Shut off fan(s) and pump(s).

  2. Remove the access panel.

  3. Inspect the wet deck surface for



  • obstructions

  • damages

  • corrosion

  • fouling.
    Remove any obstructions from heat transfer section(s).
    Any damages or corroded areas need to be repaired. Call your local
    BAC Balticare representative for assistance.
    Minor fouling can usually be removed chemically or by temporary
    changes to the water treatment programme. Contact your water
    treatment supplier for advice. Major fouling requires cleaning and
    flushing according to the CLEANING PROCEDURES (See page 12).
    Regular checking of the total aerobic bacteria count (TAB) and
    maintaining it within acceptable levels are the key to prevent
    fouling.
    Note: When working on fill section or above fill section, fill bundle edges
    should be protected from damage by service personnel, tools or debris by
    placing a temporary cover of plywood, or other suitable material, over the top
    of the fill bundles.
    DRIFT ELIMINATORS
    The inspection procedure is as follows :



  1. With fan(s) and pump(s) running visually check for areas with
    excessive drift loss.

  2. Shut off fan(s) and pump(s) and visually check eliminators for



  • obstructions

  • damages

  • cleanliness

  • proper fit



  1. If any of the above problems have been observed, stop fan(s)
    and pump(s) and remove eliminators.

  2. Clean eliminators from debris and foreign matter. Remove dirt
    and obstructions. Replace damaged or ineffective eliminators.

  3. Install eliminators and ensure they fit tightly with no gaps.
    WATER DISTRIBUTION
    The inspection procedure is as follows :

  4. Shut off the fan(s), but leave the pump(s) running.

  5. Check and adjust spray pressure, if required.

  6. Remove the eliminators.

  7. Check to see if the nozzles are producing the spray pattern
    shown in figure(s) below

  8. Clean water distribution from dirt and debris. Ensure spray
    branches and nozzles are in place and clean. Replace damaged
    or missing nozzles.

  9. Install eliminators and ensure they fit tightly with no gaps.

  10. Start fan(s) and pump(s).
    COMBINED INLET SHIELDS
    Combined inlet shields are installed at the air inlet side. These will
    prevent UV light from shining into the sump water and will eliminate
    the suction of large airborne impurities and debris. In addition, they
    will prevent water from splashing out of the air intake side of the
    unit during fan cycling.
    Figure 8: Removable Fill
    Figure 9: Removable Drift Eliminators
    Figure 10: Nozzle Spray Distribution Type Cooling Tower
    Figure 11: Removable Spray System
    10
    MAINTENANCE PROCEDURES
    Inspect regularly and remove foreign objects that might impair air
    passage. Replace broken and missing parts when necessary. Failure
    to replace broken shields will result in water loss due to splash out.
    You can remove the Combined Inlet Shields by simple loosening a
    single bolt on both ends of the air intake side. This allows simple
    removal of the combined inlet shields in small and easy to handle
    sections allowing full access to the sump section for maintenance.
    .
    Figure 12: Remove Combined Inlet Shields
    FAN SHAFT
    The fan shaft is fabricated from stainless steel. The exposed areas
    of the fan shaft are coated with a soft seal for added corrosion
    protection. It is recommended that the coating be inspected for
    continuity quarterly or at least every 6 months. Any signs of surface
    corrosion must be treated. This involves:

  11. Removal of the protective coating with a suitable cleaning
    medium

  12. The removal of any surface corrosion with emery cloth

  13. The re-coating of the shaft with soft seal.
    AXIAL FAN
    Due to its size and speed, the axial fan has great potential for injury
    and destruction if damaged. Inspect closely, and as required,
    replace damaged or deteriorating fan blades. Inspection should
    include the fan, fan cylinder and fan guard, and these should be
    inspected for



  • Fan blade tip clearance

  • Pitch angle

  • Bolt torque

  • Excessive vibration

  • Deterioration of fan assembly
    Correct or adjust if necessary.
    Note: Before any disassembly, fan blades and hub should be match marked
    to ensure proper blade pitch angle when reassembled.
    !
    No service work should be performed on or near the fans,
    motors, and drives or inside the unit without first ensuring the fan
    and pump motors have been isolated, tagged and locked in the
    off position.
    FAN MOTOR
    The standard fan motor for this line of units is a TEFC (Totally
    Enclosed Fan Cooled) motor. The motor with frame size smaller or
    equal than 200L has permanently lubricated ball bearings and
    special moisture protection on the bearings, shaft and windings.
    The only servicing required during operation is to clean the outside
    surface of the motor at least quarterly to ensure proper motor
    cooling. After prolonged shutdowns, the motor insulation should be
    checked with a “megger” insulation tester before restarting the
    motor.
    Do not wash down the motor unless it is IP66 rated. On a quarterly
    or six monthly basis check:

  • electric connections

  • motor protection devices

  • check amp draw

  • motor bearings for noise/overheating

  • motor holding bolts

  • external surface of motor for corrosion
    If the motor is equipped with space heaters, these must be
    activated when the motor is idle in order to prevent condensation
    inside the motor.
    !
    Do no run/start the fan motor(s) when there is no heat load.
    ELECTRIC WATER LEVEL CONTROL PACKAGE
    (OPTIONAL)
    The electric water level control package (optional) maintains a
    constant water level in the cold water sump independent of cooling
    load changes and water supply pressure variations. Ensure every six
    months that all components (valve, float switches) are operational
    and clean.
    !
    When disassembling the float switch for cleaning, make sure to
    reassemble it in exactly the same position, otherwise it will not
    function correctly.
    ACCESS DOOR
    The large access door is easily removed to provide complete access
    to drift eliminators, spray system and fill.
    Figure 13: Axial Fan on Direct Drive Unit
    MAINTENANCE PROCEDURES
    11
    !
    The access door should not be removed without first ensuring the
    fan and pump motors have been isolated, tagged and locked in
    the off position.
    To remove the door, take out the louvres from door side. Loosen and
    remove the knobs that hold the door in place. Larger units are
    provided with convenient anchor points to assist in removing the
    door and securing the door to the unit when removed.
    FAN SHAFT BEARINGS
    The fan shaft is supported by two pillow block ball bearings (see
    Figure below), each equipped with a lubrication fitting and a slinger/
    locking collar to keep out moisture.
    Under normal operating conditions the bearings should be greased
    every 1000 operating hours or at least every three months. The
    bearings should be lubricated with one of the following water
    resistant inhibited greases, which are good for ambient
    temperature ranging from - 20°C to 120 °C.



  1. Bearing with Locking collar

  2. Lubrication Fitting

  3. Extended Lubrication Line

  4. Bearing with Locking collar

  5. Lube Fitting
    Note: For grease products see Table below
    MOTOR BEARINGS
    Motors with frame size >200L (>30 kW) have grease fittings



  • grease intervals : twice a year unless otherwise shown on the
    nameplate of the motor

  • grease products : see below
    The bearings should be lubricated only with a hand grease gun. Do
    not use high-pressure grease guns, since they may rupture the
    bearing seals. When lubricating, purge the old grease from the
    bearing by gradually adding grease until a bead of new grease
    appears at the seal.
    GREASE PRODUCTS
    ADJUSTABLE MOTOR BASE
    The motor base adjusting screw (see figure below) should be coated
    every six months using a good quality corrosion inhibiting grease,
    such as one of those recommended for lubricating the fan shaft
    bearings.



  1. Motor Base locking nuts (both sides)

  2. Adjusting Screw
    Lubrication
    Figure 14: Access Door Anchor Points.
    Figure 15: Ball Bearing
    Shell Alvania grease RL3 -20°C to +120°C
    Texaco Multifak Premium 3 -30°C to +140°C
    Klüber Isoflex LDS Special A -50°C to +120°C
    Mobil Mobilith SHC 100 -40°C to +175°C
    Total Fina Elf Multis 3 -20°C to +120°C
    Table 3: Grease Products
    Figure 16: Ball Bearing
    Figure 17: Adjustable Motor Base
    12
    MAINTENANCE PROCEDURES
    MECHANICAL CLEANING
    Keeping your evaporative cooling equipment (and the associated
    system) clean will maintain its efficiency and help to prevent
    uncontrolled bacteriological growth. The recommended cleaning
    procedures are described below :

  3. Disconnect fan and pump motor(s) and shut off make-up supply.

  4. Remove screens, eliminators, access panels and doors and
    drain system. Do not remove sump strainer.

  5. Clean debris from exterior and fan(s) with soft brush, if
    necessary use water and soap.

  6. Clean interior with (soap) water and soft brush, if necessary use
    high pressure water jet.

  7. Remove any debris from water distribution system and clean any
    nozzles if clogged. If necessary nozzle and grommet may be
    removed for cleaning.

  8. Remove debris from heat transfer section (coil/fill) . Do not use
    steam or high pressure water to clean cooling tower wet deck
    surface.

  9. Flush with clean water and drain to remove accumulated dirt.

  10. Remove, clean and replace sump strainer(s).

  11. Clean debris from screens and eliminators with water jet and
    install.
    10.Remove debris from access doors and panels with soft brush
    and (soap) water and install.
    11.Close drain and open make-up supply. Fill system to overflow
    level with clean water.
    DISINFECTION
    Disinfection of your cooling system may be needed in case of high
    concentration of aerobic bacteria and/or Legionella. Disinfection is
    also recommended for evaporative cooling systems with known or
    suspected high bacteriological levels, prior to a cleaning procedure.
    Some local or national guidance also recommends disinfection
    prior to initial start up, after a prolonged shut down, after routine
    cleaning operations or when significant alterations have been made
    to the cooling system.
    Disinfection must be carried out in accordance with a proper
    procedure and take into account the safety of the cleaning and
    disinfection staff.
    Typically disinfection is achieved using a sodium hyperchloride
    solution to maintain a residual value of 5 - 15 mg/l of free chlorine
    and circulate this around the system for up to 6 hours. Higher
    chlorine levels for a shorter period are possible, but require a higher
    level of corrosion protection than galvanized steel only. Consult your
    BAC Balticare representative for further information.
    Excessive levels of chlorine must be avoided as this quickly can lead
    to corrosion and damage to your system.
    Chlorinated water should be de-chlorinated before draining and
    after disinfection the system must be thoroughly flushed through
    with clean water.
    Note: A proper regularly monitored biocide programme reduces the need for
    cleaning and disinfection actions significantly.
    Cleaning Procedures
    COMPREHENSIVE MAINTENANCE
    13
    In order to ensure maximum efficiency and minimum downtime of
    your evaporative cooling system, it is recommended to establish
    and execute a programme of preventive maintenance. Your local
    BAC Balticare representative will assist you in establishing and
    implementing such programme. The preventive maintenance
    programme must not only avoid that excessive downtime occurs
    under unforeseen and unwanted conditions, but must also ensure
    that factory authorized replacement parts are used, which are
    designed to fit and for their purpose carry the full factory warranty.
    To order factory authorized parts, contact your local BAC Balticare
    representative. Be sure you include the unit serial number when
    ordering any parts.
    To facilitate servicing of the equipment, it is suggested that the
    following parts be carried on hand :



  • Make-up float ball (if applicable)

  • Valve seal for water make-up valve

  • Fan shaft bearings

  • Spray nozzles and grommets

  • Spray distribution branch grommets

  • Set of belts
    Insist on factory authorised parts to avoid loss of efficiency or an
    operational risk, which may occur if non-authorised parts are used.
    Should the unit(s) be stored outside prior to installation and/or
    start-up for approximately one month or longer, or stored in severe
    climates, it is imperative that certain actions be performed by the
    installing contractor in order to maintain the unit in “as shipped”
    condition. These actions include but are not limited to:

  • Rotate the fan(s) once per month, at least 10 revolutions.

  • Rotate the motor shaft once per month, at least 10
    revolutions

  • Add desiccants to control panel interiors.

  • Wrap motor in non-plastic protective material.

  • Ensure hot water basins are covered.

  • Keep drains open on the cold water basins.

  • Remove and stor fan belts and access door gaskets.

  • Ensure unit(s) is stored on level ground.

  • For coil products N2 is recommended to prevent internal
    corrosion.

  • Purge old bearing grease by new grease at start of storage
    period and repeat before start-up.

  • Protect all black steel components with RUST VETO or
    equivalent corrosion protective material.
    For complete instructions, please contact your local BAC-Balticare
    Representative
    About Comprehensive Maintenance
    Prolonged Outdoor Storage
    14
    FURTHER ASSISTANCE & INFORMATION
    BAC has established a specialized independent total care company
    called Balticare . The BAC Balticare offering involves all elements
    required to ensure a safe and efficient operation of your evaporative
    cooling products. From a full range of risk assessment to selective
    water treatment, training, testing, record keeping and annual
    system overview. For more details, contact BAC Balticare at
    www.balticare.com or you can also contact your local BAC
    representative for further information and specific assistance at
    www.BaltimoreAircoil.eu.
    REFERENCE LITERATURE

  • Eurovent 9-5 (6) Recommended Code of Practice to keep your
    Cooling System efficient and safe. Eurovent/Cecomaf, 2002,
    30p.

  • Guide des Bonnes Pratiques, Legionella et Tours
    Aéroréfrigérantes. Ministères de l’Emploi et de la Solidarité,
    Ministère de l’Economie des Finances et de l’Industrie,
    Ministère de l’Environnement, Juin 2001, 54p.

  • Voorkom Legionellose. Minsterie van de Vlaamse
    Gemeenschap. December 2002, 77p.

  • Legionnaires’ Disease. The Control of Legionella Bacteria in
    Water Systems. Health & Safety Commission. 2000, 62p.

  • Hygienische Anforderungen an raumlufttechnische Anlagen.
    VDI 6022.


Summarize English and Arabic text online

Summarize text automatically

Summarize English and Arabic text using the statistical algorithm and sorting sentences based on its importance

Download Summary

You can download the summary result with one of any available formats such as PDF,DOCX and TXT

Permanent URL

ٌYou can share the summary link easily, we keep the summary on the website for future reference,except for private summaries.

Other Features

We are working on adding new features to make summarization more easy and accurate


Latest summaries

Aim: To underst...

Aim: To understand the importance of insulin adherence and factors affecting patients’ use of insuli...

* كيف اسوي rout...

* كيف اسوي route لل domain بحيث افعل تحديثات ثم احوله على موقعي وهكذا * لتحقيق ذلك، أفضل طريقة هي ا...

تــعلّق الــشعب...

تــعلّق الــشعب الــجزائري بالحرية : إذا كان الأحرار في كل الشعوب المستعمرة قد تغنوا بالحرية ...

The competition...

The competition section of the business plan aims to show who you are competing with, and why the be...

قُتل شاب، الثلا...

قُتل شاب، الثلاثاء، برصاص مجهولين في مدينة إب، وسط اليمن، في حادثة جديدة تعكس تصاعد حالة الانفلات ال...

إن معنى الحياة ...

إن معنى الحياة الأبدية، هذا يظهر جليا في الفصل الذي يتحدث عن قيامة لعازر من آمن بي وإن مات، فسيحيا، ...

استناداً إلى كت...

استناداً إلى كتاب السيد محافظ حمص رقم 4128/ط تاريخ 31/12/2025 وحاشيتكم المسطرة عليه بتكليفي بإجراء ا...

Side panel Sayl...

Side panel Saylor University History of Psychology Back to '1.2: History of Psychology\' Completion...

شهدت الأبحاث ال...

شهدت الأبحاث الطبية والنفسية في السنوات الأخيرة زيادة في الاهتمام بالأمراض المزمنة، بسبب ما تسببه من...

محادثة مع Gemin...

محادثة مع Gemini اريد الاجابة المنطقية والواقعية لديوان المحاسبة الاردني الوحدة 3: كيف يمكن لمدقق في...

الفصل بين السلط...

الفصل بين السلطات والتعاون فيما بينهما . نظام الحكم في دولة الكويت ، يعمل في ظل هيكل دستوري فريد ، ي...

السيادة في الدو...

السيادة في الدولة الفدرالية لا يمكن أن يتوافق مفهوم السيادة في الدولة الدستورية مع الفصل بين السلطات...